The following proposed schedule is subject to change and will be updated twice a day at 9am and 4pm to allow residents
to plan for the following day.
Thursday, July 24 -- Construction commenced today and progressed with one lane traffic. The contractor will
be be leaving one lane traffic open all evening until 8:30am Friday morning.
Friday, July 25 -- Construction was carried out from 8:30am and the roadway was closed to through traffic. At
6pm the roadway was opened to one way traffic and remained open for the weekend. Patrons of the Tennis Courts are encouraged
to park at an alternate location to avoid the construction site.
Monday, July 28 -- Construction commenced at 8:30am and the roadway was closed to through traffic. At
6pm the roadway will be opened to one way traffic.
Tuesday, July 29 -- Construction will commence at 8:30am and the roadway will be closed to through traffic. At
6pm the roadway will be opened to one way traffic.
Wednesday, July 30 -- Construction will commence at 8:30am and the roadway will be closed to through traffic. At
6pm the roadway will be opened to one way traffic.
Due to poor subsurface conditions, construction has been delayed. We anticipate construction to be
completed by Friday August 1, 2008 @ 6:00 pm.
Thursday, July 31 -- Construction commenced at 8:30am and the roadway was closed to through traffic. At 6pm
the roadway was opened to one way traffic.
Friday, August 1 -- Construction commenced at 8:30am and the roadway was closed to through traffic. At 6pm
the roadway was opened to two way traffic. The sanitary renewal portion of the construction is complete. The construction
crews will be working over the next two weeks to prepare the road for paving, this work will be done while keeping
the roadway open to at least one way traffic.
Thank you for your patience and if you have any questions please call our office at 632-9010 to speak with Darcy Harris,